What is CDM, and does it apply to domestic projects?
The Construction (Design and Management) Regulations, governing health and safety in construction — and yes, they apply to domestic projects, which surprises almost every homeowner having work done.
What the regulations require. Duties are placed on everyone involved in a construction project, to plan, manage and monitor the work so it is carried out safely, and to coordinate between designers and contractors so that risks are designed out where possible rather than managed on site.
The roles:
Client — has duties to make suitable arrangements, allow adequate time and resource, and provide information.
Principal designer — plans and coordinates health and safety during the design phase. Required where there is more than one contractor.
Principal contractor — plans and coordinates during construction. Also required where there is more than one contractor.
Designers and contractors, each with duties within their own work.
How it works for domestic clients — this is the part worth knowing. A domestic client is someone having work done on their own home not in connection with a business. Their client duties are normally transferred by the regulations:
To the contractor, where there is only one.
To the principal contractor, where there is more than one.
Or to the principal designer, if there is a written agreement to that effect.
So a homeowner does not personally carry the client duties in most cases — but the duties still exist and must be discharged by someone, and the project must have a principal designer and principal contractor appointed where more than one contractor is involved.
What this means practically:
Ask who has been appointed to these roles on your project. On a domestic extension with a builder, an electrician and a plumber, there is more than one contractor.
A construction phase plan is required for every project, however small — it need not be elaborate, and its absence indicates a contractor unfamiliar with the regulations.
Notification to the HSE is required for projects above a duration and workforce threshold.
Why it matters to you. Construction has among the highest fatality rates of any sector, and the people at risk on your project include your neighbours and your family.